to days progress. mostly on upper pond work and running of water to filter house i went for cheap method
and repair of infinity window. first we ran the hose and put new taps on.
new taps hozellock 2 way tap the hose will be buried under indian stone slabs.
then it runs along side pond to upper pond and through wall at the bottom

across bottom of upper pond which i explained earlier will be from 2 foot from boom with reinforced board fibre glassed.

then out the far side hozelock 4 way tap then from the tap to filter house

and thats it now in the filter house to connect to the draco drum. this will be permanently
switched on running. a the draco is automatic and senses when it needs a clean. its 58 micro
mesh so what happens is as the micro holes fill with muck the water rises and trigger s the
jets to activate. wash it down well blast it. and the waste runs to drain where you saw that
black ribbed hose at my drain. no more cleaning hopefully. gin clear pond simple oh yyeeaagh

picture of block work been finished on inside of upper pond.noticed the back of upper pond
where bricks are on the right red bricks this is the hight. where you see block and brick at the
front. this is where water fall will come in to main pond. water level will be one block down at back

top view in to upper pond.see the blocks in corners that s where reinforced board will sit on
then fibre glassed from there upwards so underneath will be hollow. and from the board upwards this will have gravel
and plants. to help clean pond.plus it will put oxygen in the pond, even though i will be pumping
air through bottom drain. that will be natures way.

view from other side of upper pond

repair on window brick work

that s it for today s update enjoy all the best fred